Barcloy Hill Wind Farm (12.5 MW)

Barcloy Hill Wind Farm is a 12.5 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 July 2015; the record was last updated on 29 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
refused on appealstatus in REPD
29 July 2015record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
21 December 2012Application submitted
18 July 2014Refused by the planning authority
17 October 2014Appeal lodged
23 July 2015Appeal refused

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
refused on appeal
Record last updated
29 July 2015
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Dumfries and Galloway
Planning application reference
12/P/2/0357
Appeal reference
PPA-170-2099
Turbines
5
Address (REPD)
Kirkcudbright, Dumfries and Galloway
Council area (by location)
Dumfries and Galloway
Time to decision
82 weeks
REPD reference
4515

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chapmans Howe Wind Farmwind farm6.9refused on appeal1.2
Mayfield Community Wind Farmwind farm20.4refused on appeal3.4
Solar Park & Battery Storage at Little Drum Near High Bankssolar farm36approved, not built5.2
High Nunton Farm Solar Farm & Battery Storagesolar farm49.9approved, not built10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8569, -3.9597).