Barnbackle Windfarm (5 MW)

Barnbackle Windfarm is a 5 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 November 2011; the record was last updated on 25 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
refusedstatus in REPD
25 September 2014record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
8 January 2007Application submitted
28 November 2011Refused by the planning authority

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
25 September 2014
Operator or applicant
Natural Power Consultants
Planning authority
Dumfries and Galloway
Planning application reference
07/P/2/0006
Turbines
2
Address (REPD)
Barnbackle Hill, 2km west of Lochfoot
Council area (by location)
Dumfries and Galloway
Time to decision
255 weeks
REPD reference
4506

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.04, -3.7636).