Ewe Hill (13.8 MW wind farm)

Ewe Hill is a 13.8 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 May 2016; the record was last updated on 26 October 2016. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
26 October 2016record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
7 April 2004Application submitted
7 June 2010Section 36 consent granted (Scottish Ministers)
10 September 2015Construction started
30 May 2016Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
26 October 2016
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
IEC3/107
Turbines
6
Address (REPD)
Near Langham and Lockerbie Dumfries
Council area (by location)
Dumfries and Galloway
Time to decision
322 weeks
REPD reference
4015

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ewe Hill (extension)wind farm36.8operational<0.1
Minscawind farm36.8operational2.1
Newfieldwind farm63refused3.9
Arla Lockerbie Creamery Solar Farmsolar farm5application submitted5.1
Little Hartfell Wind Farmwind farm50.4application withdrawn8.2
Land At Hartwood Hillwind farm21application withdrawn8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1071, -3.3339).