Solwaybank Wind Farm (30 MW)

Solwaybank Wind Farm is a 30 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2020; the record was last updated on 25 May 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
operationalstatus in REPD
25 May 2022record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
8 November 2011Application submitted
5 March 2014Refused by the planning authority
24 September 2014Planning permission granted
24 September 2014Appeal allowed
15 August 2018Construction started
1 November 2020Operational

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
operational
Record last updated
25 May 2022
Operator or applicant
The Renewables Infrastructure Group (TRIG)
Planning authority
Dumfries and Galloway
Planning application reference
11/P/4/0354
Turbines
15
Address (REPD)
Allfornought Hill, Langholm, Dumfries & Galloway (8 km south-west of Langholm and 12 km north of Gretna)
Council area (by location)
Dumfries and Galloway
Time to decision
150 weeks
Contracts for Difference
AR1
REPD reference
4449

Earlier applications for this site

ApplicationMWSubmittedOutcome
Solwaybank 09/P/4/02384218 June 2009withdrawn 1 July 2010

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bloch Wind Farm & Battery Storage (Solway Bank Extension)wind farm126application submitted3.1
Wind Farm & Battery Storage at Callisterhall Wind Farmwind farm39.2refused4.8
Craig Wind Farmwind farm10operational7.5
Loganhead Wind Farmwind farm53.8application submitted7.9
Gretna Green Battery Storagebattery storage456approved, not built8.7
Crossdykeswind farm48operational9.4
Hopsrig Wind Farmwind farm79.2application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1002, -3.1078).