Gretna Green Battery Storage (456 MW)

Gretna Green Battery Storage is a 456 MW battery storage project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 March 2025, not yet built; the record was last updated on 6 May 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

456 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
30 April 2024Application submitted
17 March 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (stand-alone storage)
Capacity
456 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Gresham House Devco Pipeline
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004986
Address (REPD)
South of Gretna 400kv Substation, Gretna
Council area (by location)
Dumfries and Galloway
Time to decision
46 weeks
REPD reference
15427

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Beck Burnwind farm31operational2.7
West Scales Energy Parkwind farm24.8application submitted6.1
West Scales Energy Parksolar farm12application submitted6.1
West Scales Energy Parkbattery storage12application submitted6.2
West Scales Wind Farmwind farm16.5application withdrawn6.8
Solwaybank Wind Farmwind farm30operational8.7
Todhills and Westlinton - Harker Battery Energy Storage Facilitybattery storage200approved, not built8.9
Hallburn Farmwind farm13.2operational9.1
Bloch Wind Farm & Battery Storage (Solway Bank Extension)wind farm126application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0285, -3.0545).