Energy Projects Near You

Hopsrig Wind Farm (79.2 MW)

Hopsrig Wind Farm is a 79.2 MW wind farm project in Dumfries and Galloway, Scotland. Its status: consented by Scottish Ministers on 24 September 2026, not yet built (Scottish Government Energy Consents Unit). The Renewable Energy Planning Database (July 2026 extract) still records: application submitted on 23 October 2020, no decision recorded; the record was last updated on 10 February 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

79.2 MWwind farm
approved, not builtstatus (Scottish Government Energy Consents Unit; status in REPD: application submitted)
10 February 2026record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
23 October 2020Application submitted
24 September 2026Section 36 consent granted (Scottish Ministers)

Status source: Scottish Government Energy Consents Unit. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “application submitted”.

Project details

Technology
wind farm
Capacity
79.2 MW
Status
approved, not built (Scottish Government Energy Consents Unit; REPD: application submitted)
Record last updated
10 February 2026
Operator or applicant
Muirhall Energy Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002160
Turbines
12
Turbine height
200 m
Address (REPD)
west of the B709, approximately 7.5 km north-west of Langholm and 15 km north-east of Lockerbie
Council area (by location)
Dumfries and Galloway
Contracts for Difference
AR7a
REPD reference
11065

The scheme also includes 14.1 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Loganhead Wind Farmwind farm53.8application submitted2.2
Crossdykeswind farm48operational3.1
Craig Wind Farmwind farm10operational4.4
Wind Farm & Battery Storage at Callisterhall Wind Farmwind farm39.2refused4.9
Little Hartfell Wind Farmwind farm50.4application withdrawn8.1
Bloch Wind Farm & Battery Storage (Solway Bank Extension)wind farm126application submitted8.5
Corbie Shankwind farm150application withdrawn9.4
Solwaybank Wind Farmwind farm30operational9.6
Faw Side Community Wind Farmwind farm315refused10.0

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1858, -3.1269).