Faw Side Community Wind Farm (315 MW)

Faw Side Community Wind Farm is a 315 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 December 2023; the record was last updated on 9 January 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

315 MWwind farm
refusedstatus in REPD
9 January 2024record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
22 May 2019Application submitted
22 December 2023Refused by the planning authority

Project details

Technology
wind farm
Capacity
315 MW
Status (REPD)
refused
Record last updated
9 January 2024
Operator or applicant
Community Windpower
Planning authority
Scottish Government (S36)
Planning application reference
ECU00001833
Turbines
45
Turbine height
200 m
Address (REPD)
Land 6.7km North of Langholm and 17.8 km south west of Hawick
Council area (by location)
Dumfries and Galloway
Time to decision
239 weeks
REPD reference
6459

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Corbie Shankwind farm150application withdrawn0.6
Hopsrig Wind Farmwind farm79.2application submitted10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2539, -3.0241).