Craig Wind Farm (10 MW)
Craig Wind Farm is a 10 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2007; the record was last updated on 7 January 2015.
10 MWwind farm
operationalstatus in REPD
7 January 2015record last updated
Dumfries and Gallowaycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 23 July 2003 | Application submitted |
| 24 December 2003 | Refused by the planning authority |
| 9 November 2004 | Planning permission granted |
| 9 November 2004 | Appeal allowed |
| 1 October 2007 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- operational
- Record last updated
- 7 January 2015
- Operator or applicant
- Craig Wind Farm Co
- Planning authority
- Dumfries and Galloway
- Planning application reference
- 03/P/4/0326
- Appeal reference
- PPA-170-117
- Turbines
- 4
- Address (REPD)
- Westerkirk
- Council area (by location)
- Dumfries and Galloway
- Time to decision
- 68 weeks
- REPD reference
- 4524
Who decides
| Applications | Dumfries and Galloway | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 106 | 10,236 |
| Refused | 40 (38%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 33 of 72 | 45% |
| Battery storage refused | 6 of 16 | 16% |
| Median time from submission to decision | 60.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 19 / 17 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Loganhead Wind Farm | wind farm | 53.8 | application submitted | 2.3 |
| Hopsrig Wind Farm | wind farm | 79.2 | application submitted | 4.4 |
| Wind Farm & Battery Storage at Callisterhall Wind Farm | wind farm | 39.2 | refused | 4.4 |
| Bloch Wind Farm & Battery Storage (Solway Bank Extension) | wind farm | 126 | application submitted | 5.2 |
| Crossdykes | wind farm | 48 | operational | 6.7 |
| Solwaybank Wind Farm | wind farm | 30 | operational | 7.5 |
| Corbie Shank | wind farm | 150 | application withdrawn | 9.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1641, -3.069).