Energy Projects Near You

Codrington Road (18.8 MW solar farm)

Codrington Road is an 18.8 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 August 2023, not yet built; the record was last updated on 20 July 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.8 MWsolar farm
approved, not builtstatus in REPD
20 July 2022record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
11 October 2022Application submitted
11 August 2023Planning permission granted
11 August 2026Permission expired

Project details

Technology
solar farm
Capacity
18.8 MW
Status (REPD)
approved, not built
Record last updated
20 July 2022
Operator or applicant
Renewable Connections Limited
Planning authority
South Gloucestershire
Planning application reference
P22/05906/F
Site area
26.2 ha
Address (REPD)
Codrington Road, Bristol
Council area (by location)
South Gloucestershire
Time to decision
43 weeks
Name in REPD
Codrington Road - Solar Photovoltaic Panels
REPD reference
11693

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mousewell Farm, Besom Lane Solar Farmsolar farm22application submitted0.9
Westerleigh Hill, Westerleighbattery storage200approved, not built1.8
Ring O Bells Farmsolar farm5operational3.1
Says Court Farm solar parksolar farm19.8operational3.1
Says Court Farm, Coalpit Heathbattery storage50approved, not built3.1
Elm Farm solar farm and Battery storagesolar farm24refused5.6
Perrinpit Farmsolar farm49.9under construction6.5
Green Farmsolar farm9.4refused on appeal6.9
Patch Elm Lanebattery storage35approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5123, -2.4201).