Brockworth Road (20 MW battery storage)

Brockworth Road is a 20 MW battery storage project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 April 2024, not yet built; the record was last updated on 30 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtstatus in REPD
30 May 2024record last updated
Tewkesburycouncil area

Planning timeline

DateStage
24 November 2023Application submitted
25 April 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
30 May 2024
Operator or applicant
Exagen
Planning authority
Tewkesbury
Planning application reference
23/01078/FUL
Address (REPD)
W/O Brockworth Road, N/O The A417 & E/O M5, Gloucester
Council area (by location)
Tewkesbury
Time to decision
22 weeks
Name in REPD
Brockworth Road - Battery Storage System
REPD reference
15518

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Registry Twyver House, Bruton Wayrooftop solar8.8application withdrawn5.9
Brookthorpe Solar Farmsolar farm8approved, not built6.0
Sudmeadow Road, Hempstedbattery storage50approved, not built7.0
Bristol Roadbattery storage20permission expired7.1
Solar Array at W/O Twigworth And E/O Coxs Brooksolar farm16approved, not built7.5
Hayden Hill Fruit Farmsolar farm5refused8.3
Over Farmsolar farm9.9approved, not built8.5
Bengrove Farm, Base Lanebattery storage49.9application submitted8.9
Bengrove Farm, Base Lane Solar Farmsolar farm15approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8427, -2.1619).