Hayden Hill Fruit Farm (5 MW solar farm)

Hayden Hill Fruit Farm is a 5 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 April 2016; the record was last updated on 4 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
4 May 2016record last updated
Tewkesburycouncil area

Planning timeline

DateStage
11 September 2015Application submitted
12 April 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
4 May 2016
Operator or applicant
Blue Planet Solar
Planning authority
Tewkesbury
Planning application reference
15/00982/FUL
Site area
15.3 ha
Address (REPD)
Hayden Hill Fruit Farm, Old Gloucester Road, Hayden, Cheltenham
Council area (by location)
Tewkesbury
Time to decision
31 weeks
REPD reference
5826

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Home Farmsolar farm6.7operational4.0
Tredington House Farm, Tredingtonbattery storage40approved, not built5.0
Troughton Farmsolar farm30operational5.0
Solar Array at W/O Twigworth And E/O Coxs Brooksolar farm16approved, not built6.7
Claydon Farmsolar farm18.2abandoned7.3
Bengrove Farm, Base Lane Solar Farmsolar farm15approved, not built7.6
Bengrove Farm, Base Lanebattery storage49.9application submitted7.6
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built7.8
Brockworth Roadbattery storage20approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9157, -2.1384).