Energy Projects Near You

Claydon Farm Solar Farm & Battery Storage (49.9 MW)

Claydon Farm Solar Farm & Battery Storage is a 49.9 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 December 2021, not yet built; the record was last updated on 17 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
17 December 2021record last updated
Tewkesburycouncil area

Planning timeline

DateStage
21 January 2021Application submitted
17 December 2021Planning permission granted
17 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 December 2021
Operator or applicant
JBM Solar Projects 17 Limited
Planning authority
Tewkesbury
Planning application reference
21/00259/FUL
Site area
106.7 ha
Address (REPD)
Land At Claydon Farm Claydon Tewkesbury
Council area (by location)
Tewkesbury
Time to decision
47 weeks
Contracts for Difference
AR4
Name in REPD
Claydon Farm - Solar Farm & Battery Storage
REPD reference
8038

The scheme also includes 49.9 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Claydon Farmsolar farm18.2abandoned0.9
Troughton Farmsolar farm30operational2.9
Northway Lane Waste Transfer Stationbattery storage7abandoned3.1
Tredington House Farm, Tredingtonbattery storage40approved, not built3.5
Home Farmsolar farm6.7operational5.2
Hayden Hill Fruit Farmsolar farm5refused7.8
Strensham Wind Clusterwind farm6application withdrawn7.9
Home Farmsolar farm25approved, not built8.7
Home Farmsolar farm25approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9817, -2.0999).