Energy Projects Near You

Home Farm (25 MW solar farm, REPD 14304)

Home Farm is a 25 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 May 2025, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Wychavoncouncil area

Planning timeline

DateStage
26 June 2023Application submitted
16 May 2025Planning permission granted
16 May 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Canadian Solar / Novergy
Planning authority
Wychavon
Planning application reference
23/00499/FUL
Site area
66.7 ha
Address (REPD)
Home Farm Twyning Road Strensham
Council area (by location)
Wychavon
Time to decision
99 weeks
REPD reference
14304

Recorded together with Makin Metal Powders Limited, Buckley Road (0.7 MW rooftop solar, approved, not built).

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Home Farmsolar farm25approved, not built0.9
Glebe Farm Solar Farmsolar farm32operational1.4
Strensham Wind Clusterwind farm6application withdrawn1.6
Lower Strensham, Bourne Road (Extension)solar farm8operational2.0
Croome Airfield Solar Farmsolar farm49.9operational3.4
Defford Aerodromesolar farm49.9permission expired3.4
Northway Lane Waste Transfer Stationbattery storage7abandoned6.6
Whitehouse Farm Energy Barnbattery storage40approved, not built8.9
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.058, -2.1606).