Energy Projects Near You

Glebe Farm Solar Farm (32 MW)

Glebe Farm Solar Farm is a 32 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2021; the record was last updated on 3 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWsolar farm
operationalstatus in REPD
3 September 2020record last updated
Wychavoncouncil area

Planning timeline

DateStage
21 May 2015Application submitted
21 October 2015Planning permission granted
1 June 2020Construction started
1 March 2021Operational

Project details

Technology
solar farm
Capacity
32 MW
Status (REPD)
operational
Record last updated
3 September 2020
Operator or applicant
NextEnergy Capital LLP
Planning authority
Wychavon
Planning application reference
15/01323
Site area
39.1 ha
Address (REPD)
Glebe Farm, Bourne Road, Defford, Worcester,
Council area (by location)
Wychavon
Time to decision
22 weeks
REPD reference
5480

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Strensham, Bourne Road (Extension)solar farm8operational0.5
Home Farmsolar farm25approved, not built1.4
Croome Airfield Solar Farmsolar farm49.9operational2.2
Defford Aerodromesolar farm49.9permission expired2.2
Home Farmsolar farm25approved, not built2.3
Strensham Wind Clusterwind farm6application withdrawn2.7
Northway Lane Waste Transfer Stationbattery storage7abandoned7.6
Whitehouse Farm Energy Barnbattery storage40approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0692, -2.1498).