Home Farm (25 MW solar farm, REPD 7557)

Home Farm is a 25 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 June 2025, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Wychavoncouncil area

Planning timeline

DateStage
27 June 2023Application submitted
16 June 2025Planning permission granted
16 June 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Canadian Solar / Novergy
Planning authority
Tewkesbury
Planning application reference
W/23/01011/FUL
Site area
66.7 ha
Address (REPD)
Land At Home Farm, Twyning Road, Strensham, Worcester
Council area (by location)
Wychavon
Time to decision
103 weeks
Contracts for Difference
AR7a
REPD reference
7557

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Strensham Wind Clusterwind farm6application withdrawn0.9
Home Farmsolar farm25approved, not built0.9
Glebe Farm Solar Farmsolar farm32operational2.3
Lower Strensham, Bourne Road (Extension)solar farm8operational2.8
Croome Airfield Solar Farmsolar farm49.9operational4.3
Defford Aerodromesolar farm49.9permission expired4.3
Northway Lane Waste Transfer Stationbattery storage7abandoned5.7
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built8.7
Whitehouse Farm Energy Barnbattery storage40approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0499, -2.1611).