Northway Lane Waste Transfer Station (7 MW battery storage)

Northway Lane Waste Transfer Station is a 7 MW battery storage project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 31 January 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWbattery storage
abandonedstatus in REPD
31 January 2019record last updated
Tewkesburycouncil area

Planning timeline

DateStage
31 January 2017Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
7 MW
Status (REPD)
abandoned
Record last updated
31 January 2019
Operator or applicant
Aura Power
Planning authority
Tewkesbury
Planning application reference
17/00117/FUL
Address (REPD)
Waste Transfer Station, Northway Lane, Tewkesbury, Gloucestershire
Council area (by location)
Tewkesbury
REPD reference
7125

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built3.1
Claydon Farmsolar farm18.2abandoned4.0
Tredington House Farm, Tredingtonbattery storage40approved, not built4.6
Troughton Farmsolar farm30operational4.8
Strensham Wind Clusterwind farm6application withdrawn5.0
Home Farmsolar farm25approved, not built5.7
Home Farmsolar farm25approved, not built6.6
Glebe Farm Solar Farmsolar farm32operational7.6
Home Farmsolar farm6.7operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0019, -2.1314).