Home Farm (6.7 MW solar farm)

Home Farm is a 6.7 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 30 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.7 MWsolar farm
operationalstatus in REPD
30 June 2017record last updated
Tewkesburycouncil area

Planning timeline

DateStage
3 March 2015Application submitted
22 October 2015Planning permission granted
15 November 2016Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
6.7 MW
Status (REPD)
operational
Record last updated
30 June 2017
Operator or applicant
Wirsol Energy
Planning authority
Tewkesbury
Planning application reference
15/00238/FUL
Site area
10.0 ha
Address (REPD)
Home Farm, Brockhampton Lane, Brockhampton
Council area (by location)
Tewkesbury
Time to decision
33 weeks
REPD reference
5090

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Troughton Farmsolar farm30operational3.4
Hayden Hill Fruit Farmsolar farm5refused4.0
Tredington House Farm, Tredingtonbattery storage40approved, not built4.3
Claydon Farmsolar farm18.2abandoned4.4
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built5.2
Northway Lane Waste Transfer Stationbattery storage7abandoned7.9