Claydon Farm (18.2 MW solar farm)

Claydon Farm is an 18.2 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 17 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.2 MWsolar farm
abandonedstatus in REPD
17 February 2016record last updated
Tewkesburycouncil area

Planning timeline

DateStage
25 September 2014Application submitted
5 February 2015Planning permission granted
5 January 2018Permission expired

Project details

Technology
solar farm
Capacity
18.2 MW
Status (REPD)
abandoned
Record last updated
17 February 2016
Operator or applicant
European Energy Photovoltaics
Planning authority
Tewkesbury
Planning application reference
14/00785/FUL
Site area
25.0 ha
Address (REPD)
Land To The South Of Claydon Farm, Claydon, Pamington
Council area (by location)
Tewkesbury
Time to decision
19 weeks
REPD reference
4827

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built0.9
Troughton Farmsolar farm30operational2.6
Tredington House Farm, Tredingtonbattery storage40approved, not built3.4
Northway Lane Waste Transfer Stationbattery storage7abandoned4.0
Home Farmsolar farm6.7operational4.4
Hayden Hill Fruit Farmsolar farm5refused7.3
Strensham Wind Clusterwind farm6application withdrawn8.8
Home Farmsolar farm25approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9747, -2.0933).