Tredington House Farm, Tredington (40 MW battery storage)

Tredington House Farm, Tredington is a 40 MW battery storage project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 December 2024, not yet built; the record was last updated on 31 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
31 January 2025record last updated
Tewkesburycouncil area

Planning timeline

DateStage
16 May 2024Application submitted
10 December 2024Planning permission granted
10 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
31 January 2025
Operator or applicant
Greenfield Energy Developments Ltd
Planning authority
Tewkesbury
Planning application reference
24/00411/FUL
Address (REPD)
Part Parcel 7800 Tredington
Council area (by location)
Tewkesbury
Time to decision
30 weeks
Name in REPD
Tredington House Farm, Tredington - Battery Energy Storage Facility
REPD reference
16562

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Troughton Farmsolar farm30operational1.1
Claydon Farmsolar farm18.2abandoned3.4
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built3.5
Home Farmsolar farm6.7operational4.3
Northway Lane Waste Transfer Stationbattery storage7abandoned4.6
Hayden Hill Fruit Farmsolar farm5refused5.0
Strensham Wind Clusterwind farm6application withdrawn9.5
Solar Array at W/O Twigworth And E/O Coxs Brooksolar farm16approved, not built9.6
Bengrove Farm, Base Lanebattery storage49.9application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9604, -2.1372).