Troughton Farm (30 MW solar farm)

Troughton Farm is a 30 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 1 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
operationalstatus in REPD
1 July 2016record last updated
Tewkesburycouncil area

Planning timeline

DateStage
11 February 2013Application submitted
22 July 2014Planning permission granted
1 November 2015Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
operational
Record last updated
1 July 2016
Operator or applicant
Hive Energy
Planning authority
Tewkesbury
Planning application reference
12/01220/FUL
Site area
41.0 ha
Address (REPD)
Stoke Road, Stoke Orchard, Cheltenham
Council area (by location)
Tewkesbury
Time to decision
75 weeks
REPD reference
2080

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tredington House Farm, Tredingtonbattery storage40approved, not built1.1
Claydon Farmsolar farm18.2abandoned2.6
Claydon Farm Solar Farm & Battery Storagesolar farm49.9approved, not built2.9
Home Farmsolar farm6.7operational3.4
Northway Lane Waste Transfer Stationbattery storage7abandoned4.8
Hayden Hill Fruit Farmsolar farm5refused5.0
Strensham Wind Clusterwind farm6application withdrawn9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9592, -2.1215).