Rotherdale Farm (5 MW solar farm)

Rotherdale Farm is a 5 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2015; the record was last updated on 21 May 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
21 May 2013record last updated
Wychavoncouncil area

Planning timeline

DateStage
13 November 2012Application submitted
4 January 2013Planning permission granted
1 November 2014Construction started
1 January 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
21 May 2013
Operator or applicant
Vale Green Energy
Planning authority
Wychavon
Planning application reference
12/02528
Site area
20.5 ha
Address (REPD)
Long Lane, Tilesford, Pershore, Worcestershire
Council area (by location)
Wychavon
Time to decision
7 weeks
REPD reference
1169

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rotherdale Farm (3rd Phase)solar farm5abandoned0.9
Rotherdale Farm - extensionsolar farm9operational0.9
Bishampton Solar Farmsolar farm30under construction3.2
Lenchwickwind farm11.5refused4.6
Salford Lodgesolar farm5operational7.9
Roundhill, Earls Common Road, Stock Green Solar Farmsolar farm49.9application withdrawn8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1525, -2.0465).