Salford Lodge (5 MW solar farm)

Salford Lodge is a 5 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2015; the record was last updated on 15 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
15 June 2016record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
11 September 2014Application submitted
11 December 2014Planning permission granted
1 June 2015Construction started
1 August 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
15 June 2016
Operator or applicant
AR Partners
Planning authority
Stratford-on-Avon
Planning application reference
14/02463/FUL
Site area
11.0 ha
Address (REPD)
Salford Lodge Pitchill Evesham
Council area (by location)
Stratford-on-Avon
Time to decision
13 weeks
REPD reference
4850

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lenchwickwind farm11.5refused3.5
Bishampton Solar Farmsolar farm30under construction4.9
Rotherdale Farm (3rd Phase)solar farm5abandoned7.0
Rotherdale Farm - extensionsolar farm9operational7.0
Littleton Solar Farmsolar farm30operational7.1
Rotherdale Farmsolar farm5operational7.9
Mount Farmsolar farm22operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1567, -1.9314).