Energy Projects Near You

Solar, wind and battery projects near Alcester (B49)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of B49 (Stratford-on-Avon): 3 are waiting for a planning decision, 4 approved but not yet running, 5 operational. The largest live scheme is Wheaten Hill Farm (400 MW battery storage, application submitted on 6 August 2025, no decision recorded), 7.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
3awaiting a decision
4approved, not running
5operational

Projects within 10 km of B49

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Drayton Manor Farmsolar farmsolar farm25operationalupdated Aug 2017Jan 2015granted Jun 2015Aug 2017Stratford-on-Avon6.6
Wheaten Hill Farmbattery storagebattery storage400application submittedupdated Oct 2025Aug 2025—Oct 2025Redditch7.1
Morton Wood Farmsolar farmsolar farm4.8operationalupdated May 2016Jul 2014granted Dec 2014May 2016Wychavon7.3
Feckenham Energy Storage Systembattery storagebattery storage18application withdrawnupdated Nov 2018Apr 2017—Nov 2018Redditch7.4
Drayton Manor Farm, Alcester Road Solar Farm Phase 2solar farmsolar farm32approved, not builtupdated Nov 2023Mar 2023granted Nov 2023Nov 2023Stratford-on-Avon7.8
Salford Lodgesolar farmsolar farm5operationalupdated Jun 2016Sep 2014granted Dec 2014Jun 2016Stratford-on-Avon8.1
Astwood Lane, Feckenhambattery storagebattery storage200application withdrawnupdated May 2026Mar 2023—May 2026Redditch8.7
Burton Farmsolar farmsolar farm4.4operationalupdated Aug 2016Feb 2014granted Jul 2014Aug 2016Stratford-on-Avon8.9
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tything Road East, Kinwartonrooftop solarrooftop solar—application submitted may be out of dateupdated Jun 2023May 2023—Jun 2023Stratford-on-Avon1.0
Heming Point Roof Mounted Solar Panelsrooftop solarrooftop solar0.2operationalupdated Jun 2023Dec 2020granted Feb 2021Jun 2023Redditch7.7
Feckenham Energy Storage Systembattery storagebattery storage—application submittedupdated Jul 2025May 2025—Jul 2025Redditch7.8
Woolaston Roadbattery storagebattery storage—approved, not built may be out of dateupdated Sep 2020Aug 2020granted Dec 2020Sep 2020Redditch8.4
Astwood Lane - Greener Grid Park & Energy Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2022Jan 2021granted Jan 2022Feb 2022Redditch8.7
Millennium Hatchery, Henley Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022Stratford-on-Avon8.9
Lower Skilts Farmsolar farmsolar farm0.5application withdrawnupdated Jan 2022Mar 2020—Jan 2022Stratford-on-Avon9.3

Distance from the average position of the B49 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6014032
Rooftop solar311100.4
Battery storage62200400

MW in pipeline: pending, approved and under-construction capacity.

How Stratford-on-Avon decides solar, wind and battery applications

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in Stratford-on-Avon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near B49, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.