Energy Projects Near You

Solar, wind and battery projects near Studley (B80)

20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of B80 (Stratford-on-Avon): 5 are waiting for a planning decision, 10 approved but not yet running, 2 operational. The largest live scheme is Wheaten Hill Farm (400 MW battery storage, application submitted on 6 August 2025, no decision recorded), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects within 10 km
5awaiting a decision
10approved, not running
2operational

Projects within 10 km of B80

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Thorlux Lighting Moons, Merse Roadrooftop solarrooftop solar1.4approved, not built may be out of dateupdated Feb 2022Jan 2022granted Feb 2022Feb 2022Redditch4.3
Wheaten Hill Farmbattery storagebattery storage400application submittedupdated Oct 2025Aug 2025—Oct 2025Redditch4.6
Feckenham Energy Storage Systembattery storagebattery storage18application withdrawnupdated Nov 2018Apr 2017—Nov 2018Redditch5.8
Astwood Lane, Feckenhambattery storagebattery storage200application withdrawnupdated May 2026Mar 2023—May 2026Redditch6.4
Birmingham And Solihull Rugby Club, Forshaw Heath Lanesolar farmsolar farm1.2application submittedupdated Mar 2025Feb 2025—Mar 2025Stratford-on-Avon9.1
Smaller schemes under 1 MW, mostly rooftop solar (15)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Heming Point Roof Mounted Solar Panelsrooftop solarrooftop solar0.2operationalupdated Jun 2023Dec 2020granted Feb 2021Jun 2023Redditch1.4
Woolaston Roadbattery storagebattery storage—approved, not built may be out of dateupdated Sep 2020Aug 2020granted Dec 2020Sep 2020Redditch2.1
Millennium Hatchery, Henley Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022Stratford-on-Avon3.6
Arthur Streetrooftop solarrooftop solar0.2operationalupdated Mar 2022Jan 2022granted Mar 2022Mar 2022Redditch3.9
Lower Skilts Farmsolar farmsolar farm0.5application withdrawnupdated Jan 2022Mar 2020—Jan 2022Stratford-on-Avon3.9
Hsh Coldstores Limited, Moons Moat Driverooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted Apr 2023May 2023Redditch4.4
Sparlonz Limitedrooftop solarrooftop solar0.2approved, not builtupdated Dec 2021Oct 2021granted Dec 2021Dec 2021Redditch4.4
Trinity High School And Sixth Form Centre, Easemore Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025Redditch4.9
Sainsburys, Abbey Trading Centrerooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Redditch5.4
Tything Road East, Kinwartonrooftop solarrooftop solar—application submitted may be out of dateupdated Jun 2023May 2023—Jun 2023Stratford-on-Avon5.7
Feckenham Energy Storage Systembattery storagebattery storage—application submittedupdated Jul 2025May 2025—Jul 2025Redditch6.1
Astwood Lane - Greener Grid Park & Energy Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2022Jan 2021granted Jan 2022Feb 2022Redditch6.4
Oakland International, Seafield Lanerooftop solarrooftop solar0.4approved, not builtupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Bromsgrove7.1
Birmingham And Solihull Rugby Club, Forshaw Heath Lanebattery storagebattery storage—application submittedupdated Mar 2025Feb 2025—Mar 2025Stratford-on-Avon9.1
Poolhead Lane, Earlswoodrooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Stratford-on-Avon9.2

Distance from the average position of the B80 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm210001.2
Rooftop solar1118203.9
Battery storage73200400

MW in pipeline: pending, approved and under-construction capacity.

How Stratford-on-Avon decides solar, wind and battery applications

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in Stratford-on-Avon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near B80, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.