Drayton Manor Farm, Alcester Road Solar Farm Phase 2 (32 MW)

Drayton Manor Farm, Alcester Road Solar Farm Phase 2 is a 32 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 November 2023, not yet built; the record was last updated on 29 November 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWsolar farm
approved, not builtstatus in REPD
29 November 2023record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
1 March 2023Application submitted
7 November 2023Planning permission granted
7 November 2026Permission expired

Project details

Technology
solar farm
Capacity
32 MW
Status (REPD)
approved, not built
Record last updated
29 November 2023
Operator or applicant
Drayton Stratford
Planning authority
Stratford-on-Avon
Planning application reference
23/00039/FUL
Site area
40.2 ha
Address (REPD)
Drayton Manor Farm Alcester Road
Council area (by location)
Stratford-on-Avon
Time to decision
36 weeks
Name in REPD
Drayton Manor Farm, Alcester Road - Solar Farm Phase 2
REPD reference
13508

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Drayton Manor Farmsolar farm25operational1.2
Atherstone Hill Solar Farmsolar farm26approved, not built4.3
Land at Radbrook Pasturessolar farm20.7permission expired8.0
Crimscote Solar Farm and Storage Projectsolar farm50under construction9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1949, -1.7599).