Land at Radbrook Pastures (20.7 MW solar farm)
Land at Radbrook Pastures is a 20.7 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 August 2020; the record was last updated on 3 September 2020.
20.7 MWsolar farm
permission expiredstatus in REPD
3 September 2020record last updated
Stratford-on-Avoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 April 2015 | Application submitted |
| 30 June 2016 | Refused by the planning authority |
| 16 March 2017 | Appeal lodged |
| 10 August 2017 | Planning permission granted |
| 10 August 2017 | Appeal allowed |
| 10 August 2020 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 20.7 MW
- Status (REPD)
- permission expired
- Record last updated
- 3 September 2020
- Operator or applicant
- TGC Renewables/NESF
- Planning authority
- Stratford-on-Avon
- Planning application reference
- 15/00588/FUL
- Appeal reference
- APP/J3720/W/16/3164711
- Site area
- 39.7 ha
- Address (REPD)
- Land To The West Of, Admington, Adjacent To Preston Bushes, Preston on Stour, Stratford-On-Avon
- Council area (by location)
- Stratford-on-Avon
- Time to decision
- 119 weeks
- REPD reference
- 5421
Who decides
| Applications | Stratford-on-Avon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 8 (18%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 18.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Crimscote Solar Farm and Storage Project | solar farm | 50 | under construction | 2.6 |
| Atherstone Hill Solar Farm | solar farm | 26 | approved, not built | 4.0 |
| Blackwell Grange Solar Farm | solar farm | 5 | operational | 5.5 |
| Drayton Manor Farm, Alcester Road Solar Farm Phase 2 | solar farm | 32 | approved, not built | 8.0 |
| Drayton Manor Farm | solar farm | 25 | operational | 9.0 |
| Littleton Solar Farm | solar farm | 30 | operational | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.128, -1.7152).