Energy Projects Near You

Land at Radbrook Pastures (20.7 MW solar farm)

Land at Radbrook Pastures is a 20.7 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 August 2020; the record was last updated on 3 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWsolar farm
permission expiredstatus in REPD
3 September 2020record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
27 April 2015Application submitted
30 June 2016Refused by the planning authority
16 March 2017Appeal lodged
10 August 2017Planning permission granted
10 August 2017Appeal allowed
10 August 2020Permission expired

Project details

Technology
solar farm
Capacity
20.7 MW
Status (REPD)
permission expired
Record last updated
3 September 2020
Operator or applicant
TGC Renewables/NESF
Planning authority
Stratford-on-Avon
Planning application reference
15/00588/FUL
Appeal reference
APP/J3720/W/16/3164711
Site area
39.7 ha
Address (REPD)
Land To The West Of, Admington, Adjacent To Preston Bushes, Preston on Stour, Stratford-On-Avon
Council area (by location)
Stratford-on-Avon
Time to decision
119 weeks
REPD reference
5421

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crimscote Solar Farm and Storage Projectsolar farm50under construction2.6
Atherstone Hill Solar Farmsolar farm26approved, not built4.0
Blackwell Grange Solar Farmsolar farm5operational5.5
Drayton Manor Farm, Alcester Road Solar Farm Phase 2solar farm32approved, not built8.0
Drayton Manor Farmsolar farm25operational9.0
Littleton Solar Farmsolar farm30operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.128, -1.7152).