Solar, wind and battery projects near Chipping Campden (GL55)
17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL55 (Cotswold): 6 approved but not yet running, 10 operational. The largest live scheme is Crimscote Solar Farm and Storage Project (50 MW solar farm, under construction since 1 July 2024), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of GL55
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Norton Hallsolar farm | solar farm | 2.8 | operationalupdated Aug 2014 | Nov 2012 | granted Oct 2013 | Aug 2014 | Cotswold | 4.3 |
| Northwick Estate (Extension)solar farm | solar farm | 2.2 | operationalupdated Jul 2013 | Nov 2012 | granted Mar 2013 | Jul 2013 | Cotswold | 5.4 |
| Willersey solar farmbattery storage | battery storage | 1 | operationalupdated Feb 2019 | Nov 2016 | granted Dec 2016 | Feb 2019 | Cotswold | 5.4 |
| Springhill Solar Park (Northwick)solar farm | solar farm | 5 | operationalupdated Sep 2018 | Apr 2011 | granted Jul 2011 | Sep 2018 | Cotswold | 5.5 |
| Bibsworth Lane, Willersey Solar Farmsolar farm | solar farm | 3.2 | approved, not builtupdated Jul 2025 | Feb 2024 | granted May 2025 | Jul 2025 | Wychavon | 6.0 |
| The Rainbows Solar Farmsolar farm | solar farm | 4 | operationalupdated Feb 2017 | Feb 2013 | granted Jun 2013 | Feb 2017 | Cotswold | 6.3 |
| Blackwell Grange Solar Farmsolar farm | solar farm | 5 | operationalupdated Apr 2017 | Jul 2014 | granted Mar 2016 | Apr 2017 | Stratford-on-Avon | 7.5 |
| Land at Radbrook Pasturessolar farm | solar farm | 20.7 | permission expiredupdated Sep 2020 | Apr 2015 | granted Aug 2017 | Sep 2020 | Stratford-on-Avon | 8.0 |
| Littleton Solar Farmsolar farm | solar farm | 30 | operationalupdated Apr 2026 | Sep 2020 | granted Jun 2021 | Apr 2026 | Wychavon | 8.0 |
| Crimscote Solar Farm and Storage Projectsolar farm | solar farm | 50 | under constructionupdated Aug 2024 | Jun 2021 | granted Nov 2022 | Aug 2024 | Stratford-on-Avon | 9.0 |
| Mount Farmsolar farm | solar farm | 22 | operationalupdated Mar 2016 | May 2014 | granted Jul 2015 | Mar 2016 | Wychavon | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hangmans Hall Farm, Broad Campdenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | Cotswold | 3.0 |
| Larkstoke Farm, Admington Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Dec 2024 | granted Feb 2025 | May 2025 | Stratford-on-Avon | 5.0 |
| Peters Farm, Middle Hillrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | Cotswold | 5.8 |
| Plant Producesolar farm | solar farm | 0.1 | operationalupdated Jan 2022 | Mar 2021 | granted Feb 2022 | Jan 2022 | Wychavon | 6.6 |
| Littleton Solar Farmbattery storage | battery storage | — | operationalupdated Apr 2026 | Sep 2020 | granted Jan 2021 | Apr 2026 | Wychavon | 8.0 |
| Crimscote Solar Farm and Storage Projectbattery storage | battery storage | — | under constructionupdated Aug 2024 | Jun 2021 | granted Nov 2022 | Aug 2024 | Stratford-on-Avon | 9.0 |
Distance from the average position of the GL55 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 0 | 2 | 8 | 0 | 53.2 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.5 |
| Battery storage | 3 | 0 | 1 | 2 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Cotswold decides solar, wind and battery applications
| Applications | Cotswold | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 2 (10%) | 19% |
| Solar refused | 2 of 18 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.