Energy Projects Near You

Solar, wind and battery projects near Stratford-upon-Avon (CV37)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV37 (Stratford-on-Avon): 10 approved but not yet running, 2 operational. The largest live scheme is Crimscote Solar Farm and Storage Project (50 MW solar farm, under construction since 1 July 2024), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
0awaiting a decision
10approved, not running
2operational

Projects within 10 km of CV37

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Atherstone Hill Solar Farmsolar farmsolar farm26approved, not built may be out of dateupdated Apr 2023Jan 2023granted Apr 2023Apr 2023Stratford-on-Avon2.0
Drayton Manor Farm, Alcester Road Solar Farm Phase 2solar farmsolar farm32approved, not builtupdated Nov 2023Mar 2023granted Nov 2023Nov 2023Stratford-on-Avon3.3
Burton Farmsolar farmsolar farm4.4operationalupdated Aug 2016Feb 2014granted Jul 2014Aug 2016Stratford-on-Avon3.8
Drayton Manor Farmsolar farmsolar farm25operationalupdated Aug 2017Jan 2015granted Jun 2015Aug 2017Stratford-on-Avon4.5
Land at Radbrook Pasturessolar farmsolar farm20.7permission expiredupdated Sep 2020Apr 2015granted Aug 2017Sep 2020Stratford-on-Avon5.9
Crimscote Solar Farm and Storage Projectsolar farmsolar farm50under constructionupdated Aug 2024Jun 2021granted Nov 2022Aug 2024Stratford-on-Avon7.0
Sherbourne Solar Farmsolar farmsolar farm25approved, not builtupdated Sep 2023Feb 2023granted Aug 2023Sep 2023Stratford-on-Avon9.0
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Stratford Healthcare, Arden Streetrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Dec 2023granted Mar 2024Mar 2024Stratford-on-Avon1.5
Morrisons, Alcester Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Stratford-on-Avon1.6
National Farmers Union, Tiddington Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Dec 2023Jan 2024Stratford-on-Avon3.1
Crimscote Solar Farm and Storage Projectbattery storagebattery storage—under constructionupdated Aug 2024Jun 2021granted Nov 2022Aug 2024Stratford-on-Avon7.0
Sherbourne Solar Farmbattery storagebattery storage—approved, not builtupdated Sep 2023Feb 2023granted Aug 2023Sep 2023Stratford-on-Avon9.0
Larkstoke Farm, Admington Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Feb 2025May 2025Stratford-on-Avon9.8

Distance from the average position of the CV37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm70420133
Rooftop solar404000.9
Battery storage202000

MW in pipeline: pending, approved and under-construction capacity.

How Stratford-on-Avon decides solar, wind and battery applications

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in Stratford-on-Avon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV37, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.