Crimscote Solar Farm and Storage Project (50 MW)

Crimscote Solar Farm and Storage Project is a 50 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2024; the record was last updated on 6 August 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
under constructionstatus in REPD
6 August 2024record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
18 June 2021Application submitted
29 November 2022Planning permission granted
1 July 2024Construction started

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
under construction
Record last updated
6 August 2024
Operator or applicant
Regener8 SPV1 Limited
Planning authority
Stratford-on-Avon
Planning application reference
21/02017/FUL
Site area
59.4 ha
Address (REPD)
Crimscote WimpstoneView
Council area (by location)
Stratford-on-Avon
Time to decision
76 weeks
REPD reference
9394

The scheme also includes battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Radbrook Pasturessolar farm20.7permission expired2.6
Blackwell Grange Solar Farmsolar farm5operational4.0
Atherstone Hill Solar Farmsolar farm26approved, not built5.5
Drayton Manor Farm, Alcester Road Solar Farm Phase 2solar farm32approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1229, -1.6786).