Blackwell Grange Solar Farm (5 MW)

Blackwell Grange Solar Farm is a 5 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 26 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
26 April 2017record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
21 July 2014Application submitted
23 March 2015Refused by the planning authority
1 September 2015Appeal lodged
1 March 2016Planning permission granted
1 March 2016Appeal allowed
15 December 2016Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
26 April 2017
Operator or applicant
Conergy
Planning authority
Stratford-on-Avon
Planning application reference
14/01732/FUL
Appeal reference
APP/J3720/W/15/3132381
Site area
18.5 ha
Address (REPD)
Land To North Of Ilmington Road Blackwell
Council area (by location)
Stratford-on-Avon
Time to decision
84 weeks
REPD reference
1968

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crimscote Solar Farm and Storage Projectsolar farm50under construction4.0
Land at Radbrook Pasturessolar farm20.7permission expired5.5
Atherstone Hill Solar Farmsolar farm26approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0879, -1.6673).