Energy Projects Near You

Atherstone Hill Solar Farm (26 MW)

Atherstone Hill Solar Farm is a 26 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 April 2023, not yet built; the record was last updated on 28 April 2023. REPD records the planning permission as expiring on 11 April 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWsolar farm
approved, not builtmay be out of datestatus in REPD
28 April 2023record last updated
Stratford-on-Avoncouncil area

REPD records the planning permission as expiring on 11 April 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
27 January 2023Application submitted
11 April 2023Planning permission granted
11 April 2026Permission expired

Project details

Technology
solar farm
Capacity
26 MW
Status (REPD)
approved, not built
Record last updated
28 April 2023
Operator or applicant
Elgin Energy Services
Planning authority
Stratford-on-Avon
Planning application reference
22/03309/FUL
Site area
56.8 ha
Address (REPD)
Comfort Farm Campden Road Clifford Chambers
Council area (by location)
Stratford-on-Avon
Time to decision
11 weeks
Contracts for Difference
AR5
REPD reference
13020

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Radbrook Pasturessolar farm20.7permission expired4.0
Drayton Manor Farm, Alcester Road Solar Farm Phase 2solar farm32approved, not built4.3
Drayton Manor Farmsolar farm25operational5.4
Crimscote Solar Farm and Storage Projectsolar farm50under construction5.5
Blackwell Grange Solar Farmsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1637, -1.7237).