Drayton Manor Farm (25 MW solar farm)

Drayton Manor Farm is a 25 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 23 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
operationalstatus in REPD
23 August 2017record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
30 January 2015Application submitted
8 June 2015Planning permission granted
15 December 2015Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
operational
Record last updated
23 August 2017
Operator or applicant
Anesco
Planning authority
Stratford-on-Avon
Planning application reference
15/00326/FUL
Site area
96.7 ha
Address (REPD)
Drayton Manor Farm, Alcester Road, Stratford-On-Avon, Warwickshire
Council area (by location)
Stratford-on-Avon
Time to decision
18 weeks
REPD reference
5020

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Drayton Manor Farm, Alcester Road Solar Farm Phase 2solar farm32approved, not built1.2
Atherstone Hill Solar Farmsolar farm26approved, not built5.4
Land at Radbrook Pasturessolar farm20.7permission expired9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2003, -1.7751).