Littleton Solar Farm (30 MW)

Littleton Solar Farm is a 30 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2026; the record was last updated on 8 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
operationalstatus in REPD
8 April 2026record last updated
Wychavoncouncil area

Planning timeline

DateStage
9 September 2020Application submitted
2 June 2021Planning permission granted
27 March 2026Operational

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
operational
Record last updated
8 April 2026
Operator or applicant
Stark Energy / SSE Renewables
Planning authority
Wychavon
Planning application reference
20/01798/FUL
Site area
32.2 ha
Address (REPD)
S/O Blakes Hill, Access Off Buckle Street, Honeybourne
Council area (by location)
Wychavon
Time to decision
38 weeks
REPD reference
9038

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Farmsolar farm22operational6.3
Salford Lodgesolar farm5operational7.1
Mount Farm, Mount Pleasant Solar Farmsolar farm35approved, not built8.9
Lenchwickwind farm11.5refused9.4
Land at Radbrook Pasturessolar farm20.7permission expired9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1158, -1.8514).