Energy Projects Near You

Mount Farm, Mount Pleasant Solar Farm (35 MW)

Mount Farm, Mount Pleasant Solar Farm is a 35 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 June 2024, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
Wychavoncouncil area

Planning timeline

DateStage
4 December 2023Application submitted
7 June 2024Planning permission granted
7 June 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Mount Farm Solar Limited
Planning authority
Wychavon
Planning application reference
23/01085/FUL
Appeal reference
W/23/02423/FUL
Site area
43.3 ha
Address (REPD)
Mount Farm, Mount Pleasant, Childswickham, Broadway
Council area (by location)
Wychavon
Time to decision
27 weeks
Contracts for Difference
AR7a
Name in REPD
Mount Farm, Mount Pleasant - Solar Farm
REPD reference
15060

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Farmsolar farm22operational2.6
Littleton Solar Farmsolar farm30operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.056, -1.9371).