Mount Farm (22 MW solar farm)

Mount Farm is a 22 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 22 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
operationalstatus in REPD
22 March 2016record last updated
Wychavoncouncil area

Planning timeline

DateStage
13 May 2014Application submitted
15 September 2014Refused by the planning authority
2 February 2015Appeal lodged
6 July 2015Planning permission granted
6 July 2015Appeal allowed
15 January 2016Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
22 March 2016
Operator or applicant
INRG (Solar Park) 14
Planning authority
Wychavon
Planning application reference
14/01029
Appeal reference
APP/H1840/W/14/3001928
Site area
48.0 ha
Address (REPD)
Land off Longdon Hill, Wickhamford
Council area (by location)
Wychavon
Time to decision
60 weeks
REPD reference
2175

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Farm, Mount Pleasant Solar Farmsolar farm35approved, not built2.6
Littleton Solar Farmsolar farm30operational6.3
Springhill Solar Park (Northwick)solar farm5operational9.4
Lenchwickwind farm11.5refused9.5
Salford Lodgesolar farm5operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0719, -1.9102).