Lenchwick (11.5 MW wind farm)

Lenchwick is an 11.5 MW wind farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 31 January 2011; the record was last updated on 24 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWwind farm
refusedstatus in REPD
24 November 2015record last updated
Wychavoncouncil area

Planning timeline

DateStage
4 May 2010Application submitted
31 January 2011Refused by the planning authority

Project details

Technology
wind farm
Capacity
11.5 MW
Status (REPD)
refused
Record last updated
24 November 2015
Operator or applicant
Scottish Power Renewables
Planning authority
Wychavon
Planning application reference
10/01074
Turbines
5
Address (REPD)
Land East of Bishampton Bank, Sheriffs Lench
Council area (by location)
Wychavon
Time to decision
39 weeks
REPD reference
3587

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bishampton Solar Farmsolar farm30under construction2.4
Salford Lodgesolar farm5operational3.5
Rotherdale Farm (3rd Phase)solar farm5abandoned3.8
Rotherdale Farm - extensionsolar farm9operational3.8
Rotherdale Farmsolar farm5operational4.6
Littleton Solar Farmsolar farm30operational9.4
Roundhill, Earls Common Road, Stock Green Solar Farmsolar farm49.9application withdrawn9.5
Mount Farmsolar farm22operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1461, -1.9796).