Rotherdale Farm - extension (9 MW solar farm)

Rotherdale Farm - extension is a 9 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2015; the record was last updated on 20 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
operationalstatus in REPD
20 March 2017record last updated
Wychavoncouncil area

Planning timeline

DateStage
29 April 2014Application submitted
23 June 2014Planning permission granted
1 September 2014Construction started
1 March 2015Operational

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
operational
Record last updated
20 March 2017
Operator or applicant
Vale Green Energy
Planning authority
Wychavon
Planning application reference
W/14/00830/PN
Site area
20.5 ha
Address (REPD)
Long Lane, Tilesford, Pershore, Worcestershire
Council area (by location)
Wychavon
Time to decision
8 weeks
REPD reference
2022

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rotherdale Farm (3rd Phase)solar farm5abandoned<0.1
Rotherdale Farmsolar farm5operational0.9
Bishampton Solar Farmsolar farm30under construction2.4
Lenchwickwind farm11.5refused3.8
Salford Lodgesolar farm5operational7.0
Roundhill, Earls Common Road, Stock Green Solar Farmsolar farm49.9application withdrawn8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1536, -2.0341).