Energy Projects Near You

Springhill Solar Park (Northwick) (5 MW)

Springhill Solar Park (Northwick) is a 5 MW solar farm project in Cotswold, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2013; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Cotswoldcouncil area

Planning timeline

DateStage
18 April 2011Application submitted
21 July 2011Planning permission granted
1 February 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Greencoat Capital
Planning authority
Cotswold
Planning application reference
11/01247/FUL
Site area
19.8 ha
Address (REPD)
Chipping Campden, Gloucestershire
Council area (by location)
Cotswold
Time to decision
13 weeks
REPD reference
1053

Who decides

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Farmsolar farm22operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0188, -1.8025).