Energy Projects Near You

Solar, wind and battery projects near Moreton-in-Marsh (GL56)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL56 (Cotswold): 2 approved but not yet running, 2 operational. The largest live scheme is Hangmans Hall Farm, Broad Campden (0.2 MW rooftop solar, approved on 26 May 2023, not yet built), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
2approved, not running
2operational

Projects within 10 km of GL56

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Springhill Solar Park (Northwick)solar farmsolar farm5operationalupdated Sep 2018Apr 2011granted Jul 2011Sep 2018Cotswold7.5
Northwick Estate (Extension)solar farmsolar farm2.2operationalupdated Jul 2013Nov 2012granted Mar 2013Jul 2013Cotswold7.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hangmans Hall Farm, Broad Campdenrooftop solarrooftop solar0.2approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Cotswold6.8
Peters Farm, Middle Hillrooftop solarrooftop solar0.1approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Cotswold9.3

Distance from the average position of the GL56 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200200
Rooftop solar202000.3

MW in pipeline: pending, approved and under-construction capacity.

How Cotswold decides solar, wind and battery applications

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in Cotswold

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.