Energy Projects Near You

Solar, wind and battery projects near Chipping Norton (OX7)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of OX7 (West Oxfordshire): 1 approved but not yet running, 1 operational. The largest live scheme is Hook Norton Brewery, Brewery Lane (0.3 MW solar farm, approved on 11 March 2024, not yet built), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
1approved, not running
1operational

Projects within 10 km of OX7

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cornbury Park Estatesolar farmsolar farm5application withdrawnupdated Apr 2011Feb 2011—Apr 2011West Oxfordshire4.7
Enstone Solar Parksolar farmsolar farm1.1refusedupdated Mar 2012Dec 2011refused Feb 2012Mar 2012West Oxfordshire6.5
Southill Solarsolar farmsolar farm4.5operationalupdated Nov 2016Apr 2015granted Sep 2015Nov 2016West Oxfordshire6.7
Akeman Solar Park & Battery Storagesolar farmsolar farm20refusedupdated Sep 2025Mar 2025refused Aug 2025Sep 2025West Oxfordshire9.4
Akeman Solar Park & Battery Storagebattery storagebattery storage1.5refusedupdated Sep 2025Mar 2025refused Aug 2025Sep 2025West Oxfordshire9.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hook Norton Brewery, Brewery Lanesolar farmsolar farm0.3approved, not builtupdated Jan 2025Jan 2024granted Mar 2024Jan 2025Cherwell10.0

Distance from the average position of the OX7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm501120.3
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

How West Oxfordshire decides solar, wind and battery applications

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in West Oxfordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.