Energy Projects Near You

Akeman Solar Park & Battery Storage (20 MW)

Akeman Solar Park & Battery Storage is a 20 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 August 2025; the record was last updated on 11 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
refusedstatus in REPD
11 September 2025record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
5 March 2025Application submitted
28 August 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
refused
Record last updated
11 September 2025
Operator or applicant
British Solar Renewables
Planning authority
West Oxfordshire
Planning application reference
25/00234/FUL
Site area
45.3 ha
Address (REPD)
S/O Ramsden, Akeman Street, Ramsden, Chipping Norton
Council area (by location)
West Oxfordshire
Time to decision
25 weeks
REPD reference
18339

The scheme also includes 1.5 MW of battery storage, recorded separately in REPD (refused).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Akeman Solar Park & Battery Storage 21/02473/FUL2016 July 2021withdrawn 10 August 2022
Akeman Solar Park & Battery Storage 23/02917/FUL206 November 2023refused 5 February 2024

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built2.6
Quarry Solar Farm & Battery Storage Facilitybattery storage35approved, not built2.6
Cornbury Park Estatesolar farm5application withdrawn4.7
Eynsham Solar Farmsolar farm13.2operational6.0
Witney Bypass, Stanton Harcourt Roadbattery storage150application submitted6.8
Caswell Lane, Brize Norton Solar Farm & Battery Storagesolar farm30application submitted6.9
Ducklington Solar Farmsolar farm36under construction7.1
Aurora Solar Farmsolar farm32under construction8.1
Tar Solar Farmsolar farm49.9approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8283, -1.4931).