Eynsham Solar Farm (13.2 MW)

Eynsham Solar Farm is a 13.2 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 1 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.2 MWsolar farm
operationalstatus in REPD
1 December 2014record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
12 September 2013Application submitted
4 December 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
13.2 MW
Status (REPD)
operational
Record last updated
1 December 2014
Operator or applicant
Belltown Power
Planning authority
West Oxfordshire
Planning application reference
13/1277/P/FP
Site area
25.5 ha
Address (REPD)
Land North of Salutation Farm Barnard Gate
Council area (by location)
West Oxfordshire
Time to decision
12 weeks
REPD reference
1529

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aurora Solar Farmsolar farm32under construction2.1
Tar Solar Farmsolar farm49.9approved, not built3.9
Tar Solar Farmbattery storage40approved, not built3.9
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built4.3
Quarry Solar Farm & Battery Storage Facilitybattery storage35approved, not built4.3
Witney Bypass, Stanton Harcourt Roadbattery storage150application submitted4.9
Botley West Solar Projectsolar farm840application submitted5.7
Akeman Solar Park & Battery Storagesolar farm20refused6.0
Ducklington Solar Farmsolar farm36under construction6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.794, -1.4264).