Energy Projects Near You

Botley West Solar Project (840 MW)

Botley West Solar Project is an 840 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 November 2024, no decision recorded; the record was last updated on 16 December 2024. As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010147).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

840 MWsolar farm
application submittedstatus in REPD
16 December 2024record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
15 November 2024Application submitted

Project details

Technology
solar farm
Capacity
840 MW
Status (REPD)
application submitted
Record last updated
16 December 2024
Operator or applicant
Photovolt Development Partners / SolarFive
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010147
Site area
1,400.0 ha
Address (REPD)
Botley West, Botley, Oxford
Council area (by location)
West Oxfordshire
Name in REPD
Botley West, Botley - Botley West Solar Project
REPD reference
12588

Official project record at the Planning Inspectorate (EN010147)

According to the REPD extract for July 2026, there is still no decision on Botley West: the application was submitted on 15 November 2024, and the record has not changed since 16 December 2024. Among solar applications awaiting a decision, this is the largest one.

Who decides

At 840 MW across 1,400 hectares, with Photovolt Development Partners and SolarFive as the applicants, the scheme is a nationally significant infrastructure project, so West Oxfordshire council does not decide it. The Planning Inspectorate (EN010147) examines the application, and the Energy Secretary grants the development consent order (DCO). The Inspectorate has 46 decided applications, a median of 73 weeks and 7% refusals (all decisions).

Why you should double-check the status

Of the records marked “awaiting a decision”, 32% were submitted more than two years ago, and only 37% were updated in the last 12 months. You can check the official status in the Planning Inspectorate record via the link on the page. There is no site map in the data; the mini-map only marks the register point. Nearby, The Flit (10.5 MW) is operational and Aurora Solar Farm (32 MW) is under construction, while Botley at 50 MW is a different project: it was refused.

Who decides

As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010147). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodstock Road, Yarntonbattery storage52approved, not built3.4
Minnis Farmsolar farm5permission expired3.8
The Flitsolar farm10.5operational3.9
Blenheim Net Zero Estatesolar farm5under construction3.9
Aurora Solar Farmsolar farm32under construction5.2
Eynsham Solar Farmsolar farm13.2operational5.7
Botleysolar farm50refused7.1
Wootton Balksolar7.5refused7.5
Tar Solar Farmbattery storage40approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8132, -1.349).