Energy Projects Near You

Aurora Solar Farm (32 MW)

Aurora Solar Farm is a 32 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 26 April 2021; the record was last updated on 23 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWsolar farm
under constructionstatus in REPD
23 March 2023record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
24 September 2019Application submitted
10 February 2020Planning permission granted
26 April 2021Construction started

Project details

Technology
solar farm
Capacity
32 MW
Status (REPD)
under construction
Record last updated
23 March 2023
Operator or applicant
Low Carbon UK Solar Investment Company
Planning authority
West Oxfordshire
Planning application reference
19/02516/FUL
Site area
63.4 ha
Address (REPD)
Twelve Acre Farm, Chilbridge Road, Eynsham, Witney,
Council area (by location)
West Oxfordshire
Time to decision
20 weeks
REPD reference
7384

The scheme also includes 18 MW of battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eynsham Solar Farmsolar farm13.2operational2.1
Tar Solar Farmsolar farm49.9approved, not built3.4
Tar Solar Farmbattery storage40approved, not built3.4
Botley West Solar Projectsolar farm840application submitted5.2
Witney Bypass, Stanton Harcourt Roadbattery storage150application submitted5.7
Quarry Solar Farm & Battery Storage Facilitybattery storage35approved, not built6.3
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built6.3
Ducklington Solar Farmsolar farm36under construction7.2
Botleysolar farm50refused7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.781, -1.4036).