Botley (50 MW solar farm)

Botley is a 50 MW solar farm project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 November 2025; the record was last updated on 20 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
refusedstatus in REPD
20 March 2026record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
12 December 2024Application submitted
6 November 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
refused
Record last updated
20 March 2026
Operator or applicant
Red House Solar Limited
Planning authority
Vale of White Horse
Planning application reference
P24/V2489/FUL
Site area
63.5 ha
Address (REPD)
W/O Red House Farm, Botley, Oxford
Council area (by location)
Vale of White Horse
Time to decision
47 weeks
Name in REPD
Botley - Solar Photovoltaic Array
REPD reference
18174

Earlier applications for this site

ApplicationMWSubmittedOutcome
Botley P23/V2624/FUL5027 November 2023withdrawn 19 July 2024

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Minnis Farmsolar farm5permission expired5.2
The Flitsolar farm10.5operational5.5
Woodstock Road, Yarntonbattery storage52approved, not built5.6
Botley West Solar Projectsolar farm840application submitted7.1
Aurora Solar Farmsolar farm32under construction7.3
Wadley Hill Farmsolar farm5refused8.4
Nuneham Courtenay Solar Farmsolar farm49.9application submitted9.1
Cowley electricity sub-stationbattery storage49.9operational9.2
Tar Solar Farmbattery storage40approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7553, -1.3052).