Energy Projects Near You

Renewable energy projects in Vale of White Horse

43 solar, wind or battery projects of 150 kW or more are located in Vale of White Horse (REPD, July 2026 extract): 7 pending, 17 approved but not running, 10 operational and 2 refused. The council refused 5 of 31 decided applications (16%; UK 19%), with a median 13 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43projects in the council area
7awaiting a decision
17approved, not running
16%of decisions refused

How Vale of White Horse decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Projects in Vale of White Horse

Projects of 1 MW and more (22)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Applefordbattery storagebattery storage300approved, not builtupdated Feb 2026Jan 2025granted Aug 2025Feb 2026
Botleysolar farmsolar farm50refusedupdated Mar 2026Dec 2024refused Nov 2025Mar 2026
Barnstaples Farmsolar farmsolar farm49.9approved, not builtupdated Oct 2024Dec 2021granted Feb 2024Oct 2024
Willowfields Energy Park, Marchamsolar farmsolar farm49.9application submittedupdated Jan 2025Dec 2024—Jan 2025
Landmead Farm (East Hanney)solar farmsolar farm46operationalupdated Feb 2017Jul 2013granted Oct 2013Feb 2017
Snowswick Lane, Coleshill Solar Farmsolar farmsolar farm39.6application submittedupdated Oct 2025Aug 2025—Oct 2025
Manor Farm, Denchworthsolar farmsolar farm30approved, not builtupdated Feb 2026Nov 2023granted Apr 2025Feb 2026
Elms Farmsolar farmsolar farm29operationalupdated Mar 2015May 2014granted Aug 2014Mar 2015
Reading Roadsolar farmsolar farm25application withdrawnupdated Jul 2014Apr 2014—Jul 2014
Snowswick Lane, Coleshill Solar Farmbattery storagebattery storage25application submittedupdated Oct 2025Aug 2025—Oct 2025
Appleford Sidings, Sutton Courtenaysolar farmsolar farm24application submitted may be out of dateupdated Jun 2021May 2021—Jun 2021
Chadwicks Farmsolar farmsolar farm20refused on appealupdated Aug 2015Jan 2015refused Apr 2015Aug 2015
Willowfields Energy Park, Marchambattery storagebattery storage20application submittedupdated Jan 2025Dec 2024—Jan 2025
Hill Farm Solar Park (VoWH)solar farmsolar farm14.8operationalupdated Apr 2014Jul 2013granted Oct 2013Apr 2014
Goose Willow Farmsolar farmsolar farm11.5operationalupdated Feb 2014Oct 2012granted Dec 2012Feb 2014
Steventon Solar Parksolar farmsolar farm10operationalupdated Sep 2018Jul 2012granted Oct 2012Sep 2018
Goose Willow Farm - extensionsolar farmsolar farm7operationalupdated Jul 2016Sep 2013granted Dec 2013Jul 2016
Westmill Wind Farmwind farmwind farm6.5operationalupdated Jun 2010Sep 2000granted Jul 2005Jun 2010
Westmill Farmsolar farmsolar farm5operationalupdated Dec 2017Jan 2011granted Mar 2011Dec 2017
Radley College, Kennington Gate Solar Array & Battery Storagesolar farmsolar farm2approved, not builtupdated May 2024Apr 2023granted Aug 2023May 2024
Avon Road Car Park Solar Photovoltaic Carport Systemrooftop solarrooftop solar1.6operationalupdated Mar 2021Jan 2021granted Apr 2021Mar 2021
Rutherford Appleton Laboratoryrooftop solarrooftop solar1.6approved, not built may be out of dateupdated May 2021May 2021granted Jul 2021May 2021
Smaller schemes under 1 MW, mostly rooftop solar (21)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Rebellion Film Studios, Milton Roadrooftop solarrooftop solar0.9approved, not builtupdated Feb 2023Nov 2022granted Jan 2023Feb 2023
Hachette UK Distribution Centre, Milton Roadrooftop solarrooftop solar0.9approved, not builtupdated Mar 2026Sep 2024granted Nov 2024Mar 2026
Millets Farm Centre, Kingston Roadsolar farmsolar farm0.8approved, not built may be out of dateupdated Feb 2023Sep 2022granted Jan 2023Feb 2023
Harwell Science And Innovation Campus -Solar Panelsrooftop solarrooftop solar0.6approved, not builtupdated Feb 2025Sep 2024granted Dec 2024Feb 2025
Rutherford Appleton Laboratory, Building R105 & R106, Harwellrooftop solarrooftop solar0.6application withdrawnupdated Apr 2022Mar 2022—Apr 2022
Rutherford Appleton Laboratory, Building R1, Harwellrooftop solarrooftop solar0.4application withdrawnupdated Apr 2022Mar 2022—Apr 2022
Macdermid Autotype, Grove Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026May 2025granted Jul 2025Jan 2026
Milton Park, Miltonrooftop solarrooftop solar0.3approved, not builtupdated Jun 2025Feb 2025granted Mar 2025Jun 2025
Rutherford Appleton Laboratory, Building R8 & R9, Harwellrooftop solarrooftop solar0.3application withdrawnupdated Apr 2022Mar 2022—Apr 2022
Blacklands Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023
Rutherford Appleton Laboratory, Building R40, Harwellrooftop solarrooftop solar0.2application withdrawnupdated Apr 2022Mar 2022—Apr 2022
Rutherford Appleton Laboratory, Buildings R25, R61 & R68, Harwellrooftop solarrooftop solar0.2application withdrawnupdated Apr 2022Mar 2022—Apr 2022
Building One, Wyndyke Furlongrooftop solarrooftop solar0.2application submittedupdated Mar 2026Feb 2026—Mar 2026
South Car Park Solar photovoltaic carport systemrooftop solarrooftop solar—operationalupdated Mar 2021Jan 2021granted Sep 2021Mar 2021
Appleford Sidings, Sutton Courtenaybattery storagebattery storage—application submitted may be out of dateupdated Jun 2021May 2021—Jun 2021
Radley College, Kennington Gate Solar Array & Battery Storagebattery storagebattery storage—approved, not builtupdated May 2024Apr 2023granted Aug 2023May 2024
Westmill Farmbattery storagebattery storage—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023
Barnstaples Farmbattery storagebattery storage—approved, not builtupdated Oct 2024Apr 2020granted Feb 2024Oct 2024
The Sutton Courtenay Waste Management Site, Appleford Sidingsbattery storagebattery storage—approved, not builtupdated Feb 2026Jun 2025granted Jul 2025Feb 2026
Brook Drive, Milton Parkrooftop solarrooftop solar—approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025
Sandford Lane, Kenningtonbattery storagebattery storage—application withdrawnupdated May 2026Aug 2025—May 2026

Postcode districts in Vale of White Horse

DistrictProjects within 10 kmPendingApprovedOperational
OX1224278
OX13365196
OX14485268
SN77223

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Vale of White Horse by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.