Hill Farm Solar Park (VoWH) (14.8 MW)

Hill Farm Solar Park (VoWH) is a 14.8 MW solar farm project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.8 MWsolar farm
operationalstatus in REPD
30 April 2014record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
12 July 2013Application submitted
1 October 2013Planning permission granted
1 December 2013Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
14.8 MW
Status (REPD)
operational
Record last updated
30 April 2014
Operator or applicant
Hill Farm Solar Park Limited
Planning authority
Vale of White Horse
Planning application reference
P13/V1478/FUL
Address (REPD)
Land west of Hill Farm Steventon
Council area (by location)
Vale of White Horse
Time to decision
12 weeks
REPD reference
1331

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Reading Roadsolar farm25application withdrawn1.2
Goose Willow Farm - extensionsolar farm7operational1.8
Steventon Solar Parksolar farm10operational2.1
Goose Willow Farmsolar farm11.5operational2.2
Landmead Farm (East Hanney)solar farm46operational3.5
Elms Farmsolar farm29operational3.8
Barnstaples Farmsolar farm49.9approved, not built4.7
Chadwicks Farmsolar farm20refused on appeal5.5
Appleford Sidings, Sutton Courtenaysolar farm24application submitted5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6166, -1.348).