Energy Projects Near You

Steventon Solar Park (10 MW)

Steventon Solar Park is a 10 MW solar farm project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 June 2014; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
18 July 2012Application submitted
17 October 2012Planning permission granted
15 March 2014Construction started
19 June 2014Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Vale of White Horse
Planning application reference
P12/V1571/FUL
Site area
22.6 ha
Address (REPD)
Land to West of Steventon Field, Steventon, Abingdon, Oxon
Council area (by location)
Vale of White Horse
Time to decision
13 weeks
REPD reference
1817

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goose Willow Farmsolar farm11.5operational0.4
Goose Willow Farm - extensionsolar farm7operational0.9
Landmead Farm (East Hanney)solar farm46operational1.4
Hill Farm Solar Park (VoWH)solar farm14.8operational2.1
Barnstaples Farmsolar farm49.9approved, not built2.8
Reading Roadsolar farm25application withdrawn3.3
Chadwicks Farmsolar farm20refused on appeal3.6
Elms Farmsolar farm29operational4.1
Appleford Sidings, Sutton Courtenaysolar farm24application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6334, -1.3613).