Elms Farm (29 MW solar farm)

Elms Farm is a 29 MW solar farm project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 March 2015; the record was last updated on 17 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29 MWsolar farm
operationalstatus in REPD
17 March 2015record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
28 May 2014Application submitted
28 August 2014Planning permission granted
1 December 2014Construction started
16 March 2015Operational

Project details

Technology
solar farm
Capacity
29 MW
Status (REPD)
operational
Record last updated
17 March 2015
Operator or applicant
Bluefield Solar
Planning authority
Vale of White Horse
Planning application reference
P14/V1135/FUL
Site area
62.0 ha
Address (REPD)
Elms Farm Grove
Council area (by location)
Vale of White Horse
Time to decision
13 weeks
REPD reference
1832

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Farm Solar Park (VoWH)solar farm14.8operational3.8
Manor Farm, Denchworthsolar farm30approved, not built4.1
Steventon Solar Parksolar farm10operational4.1
Reading Roadsolar farm25application withdrawn4.5
Barnstaples Farmsolar farm49.9approved, not built4.5
Goose Willow Farmsolar farm11.5operational4.6
Landmead Farm (East Hanney)solar farm46operational4.7
Goose Willow Farm - extensionsolar farm7operational4.7
Chadwicks Farmsolar farm20refused on appeal5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6051, -1.4003).