Barnstaples Farm (49.9 MW solar farm)

Barnstaples Farm is a 49.9 MW solar farm project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 February 2024, not yet built; the record was last updated on 11 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
11 October 2024record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
3 December 2021Application submitted
28 February 2024Planning permission granted
28 February 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
11 October 2024
Operator or applicant
Nextpower SPV 14 Limited
Planning authority
Vale of White Horse
Planning application reference
P21/V3395/FUL
Site area
63.2 ha
Address (REPD)
Land at Barnstaples Farm, East Hanney, Wantage, Oxfordshire
Council area (by location)
Vale of White Horse
Time to decision
117 weeks
Contracts for Difference
AR6
REPD reference
7960

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chadwicks Farmsolar farm20refused on appeal0.8
Landmead Farm (East Hanney)solar farm46operational1.7
Steventon Solar Parksolar farm10operational2.8
Goose Willow Farmsolar farm11.5operational3.0
Goose Willow Farm - extensionsolar farm7operational3.6
Manor Farm, Denchworthsolar farm30approved, not built4.4
Willowfields Energy Park, Marchamsolar farm49.9application submitted4.4
Willowfields Energy Park, Marchambattery storage20application submitted4.4
Elms Farmsolar farm29operational4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6459, -1.3974).